The Developer Says It’s Fixing the Building – Is That Enough Under the Building Safety Act?

A developer that meets its Developer Remediation Contract may still owe more under the Building Safety Act 2022. The contract and the Act cover different defects, set different standards for the works and treat interim costs differently. For developers, that gap is a risk. For building owners and the people who manage buildings, it is an opportunity to recover more.

The key points

  • Developers who signed a Developer Remediation Contract agreed to remedy life-critical fire safety defects in buildings over 11 metres that they developed.
  • The Government enforces the DRC through the Responsible Actors Scheme. Breaching it can stop a developer building in England.
  • The Building Safety Act 2022 (‘BSA’) enables building owners, leaseholders, RTM companies and certain other interested parties to apply for wider orders. These can cover more defects, a higher standard of work and interim costs such as waking watches.
  • Agreeing the scope and standard of work early is usually cheaper for everyone than going back to the building later.

What is a Developer Remediation Contract?

A Developer Remediation Contract (DRC) is a legally binding agreement between a developer and the Government to fix historic fire safety defects at the developer’s own cost. The Government published the terms in January 2023, and eligible developers had to sign by 13 March 2023.

Under a DRC, a developer must deal with life-critical fire safety defects in residential buildings in England over 11 metres high that it developed or refurbished in the 30 years before 5 April 2022. That means more than building work. The developer must:

  • investigate and assess affected buildings
  • carry out or pay for the remediation works
  • meet the professional and project costs
  • in some cases, repay public money already spent on the building

The aim is that the developer, not leaseholders, pays for historic fire safety defects.

What happens if a developer doesn’t comply?

The DRC sets out what developers must do. The Responsible Actors Scheme (the ‘Scheme’) makes them do it. It was set up under the BSA and the Building Safety (Responsible Actors Scheme and Prohibitions) Regulations 2023.

To stay in the Scheme, a developer must keep to its DRC obligations. A developer that should join but doesn’t, or that contravenes the Scheme’s conditions, can be:

  • banned from carrying out major developments in England
  • refused certain building control approvals

For most developers, those consequences are serious enough to make DRC compliance a priority. But the Scheme only enforces the contract. It does not limit what can be claimed under the BSA.

If the developer has signed a DRC, is the building covered?

Not always. Alongside the DRC, the BSA gives building owners and others the right to apply for three types of orders:

  • Remediation Order: requires a landlord to fix specified defects by a set date.
  • Remediation Contribution Order: requires a developer, landlord or associated company to pay towards the cost of fixing defects.
  • Building Liability Order: extends a company’s building safety liability to associated companies, such as the parent of a special purpose vehicle. These are made by the High Court.

Sections 123 and 124 of the BSA create legal remedies through the First-tier Tribunal (the ‘Tribunal’) to force the fixing of historical building safety defects and to recover the financial costs from responsible parties. These orders sit outside the DRC. A developer that has done everything its DRC requires can still face one.

The defects may be different

The DRC covers ‘life-critical fire safety defects’. The BSA deals with ‘relevant defects’, which are defects that cause a building safety risk: a risk to people’s safety from the spread of fire or structural collapse. The two tests overlap, but they are not the same. A defect outside the DRC may still be a relevant defect under the BSA.

The standard of works may be different

Under the DRC, remedial works must reduce fire safety risks arising from life-critical fire safety defects to a ‘tolerable’ level. External walls are assessed using PAS 9980, the industry code of practice for appraising the fire risk of external walls. An updated version, PAS 9980:2026, was published on 15 September 2026. It continues to favour proportionate, risk-based remediation over blanket cladding removal. In many cases, we see developers suggesting schemes that encapsulate rather than remove combustible materials, as this may achieve a ‘tolerable’ risk rating under PAS 9980.

In Empire Square (June 2025), the Tribunal rejected the suggestion that remediation need only reduce risk to a ‘tolerable’ level, holding that the purpose of the Building Safety Act 2022 is to cure relevant defects. Subsequent decisions have endorsed that approach. In Canary Riverside (January 2026), the Tribunal confirmed that the statutory test is focused on practical remediation that actually remedies defects rather than merely reducing risk. Likewise, in Hallings Wharf Studios (May 2026), it rejected a cheaper remediation scheme that would have left combustible materials in place, finding that full removal was reasonable to achieve compliance with current Building Regulations.

Interim costs may be recoverable

The DRC does not generally cover interim measures, such as waking watches or temporary fire alarms. The Tribunal has allowed these costs to be recovered through Remediation Contribution Orders where they relate to relevant defects.

At a glance

Developer Remediation ContractBuilding Safety Act orders
Who enforces itGovernment, through the Responsible Actors SchemeBuilding owners, RTM companies, and other interested parties through the Tribunal or High Court
Which defectsLife-critical fire safety defectsRelevant defects (a wider test)
Standard of worksFire risk reduced to a tolerable level (PAS 9980 for external walls)Building Regulations / standards in force when works are done (Empire Square)
Interim costs, e.g. waking watchGenerally not coveredCan be recovered through a Remediation Contribution Order
Who can be liableThe developer that signedDevelopers, landlords and associated companies

An example

This example is illustrative and not based on a real building.

A developer signed a DRC for a 14-storey block. Its fire engineer assessed the external wall under PAS 9980 and recommended replacing the cladding on two elevations. The developer completed the works, and a final assessment confirmed the risk was now tolerable.

The RTM company then appointed its own fire engineer, who found missing cavity barriers behind the retained cladding and defects in the fire stopping between flats. Neither was in the developer’s scope. The RTM company had also spent £80,000 on a waking watch while it waited for the works.

The developer has met its DRC obligations. But the freeholder, or the RTM company if it qualifies as an interested person, can still apply to the Tribunal for a Remediation Contribution Order covering the remaining defects and the waking watch costs. The developer now faces a potential second project, further costs and possibly a gap in its insurance. Agreeing a full scope at the start would probably have cost less for both sides.

What this means for you

Developers

  • Meeting your DRC obligations is necessary but may not end your liability. Consider remediating to current Building Regulations from the outset, so you only go back to a building once.
  • Engage early with the building owner’s fire engineer and agree a scope before work starts.
  • Check now whether your insurance responds to Remediation Orders and Remediation Contribution Orders.
  • Remember that Building Liability Orders and Remediation Contribution Orders can reach associated companies. A special purpose vehicle may not shield the wider group.

RTM companies

  • Obtain legal advice to confirm whether you are an ‘interested person’ who can apply for an order, or whether the landlord needs to bring the claim.
  • Keep records of every interim cost, such as waking watches, alarms and fire risk assessments. These may be recoverable.
  • Don’t approve a developer’s proposals without legal advice and your own fire engineer’s review.

Leaseholder-owned freeholds

  • As landlord, you can apply for orders against the developer and its associated companies. But you can also be the subject of orders under the BSA, so understand both sides.
  • If the developer’s works fall short, the cost may fall on you and, through the service charge, your members.

Property managers

  • You are often the first contact when a developer proposes works. Know when to bring in your client and their legal advisers.
  • Keep a clear record of defects, interim measures and costs. That evidence is central to any claim.
  • Share this article with client boards and residents to explain where they stand.

How we can help

Colman Coyle advises developers, RTM companies, leaseholder-owned freeholds and property managers on building safety remediation and disputes.

If a developer has approached you with a remediation proposal, or you are a developer reviewing your exposure beyond your DRC, please contact Anjani Purohit at anjani.purohit@colmancoyle.com or Elizabeth Harland at elizabeth.harland@colmancoyle.com